Kitui County Stalled Projects (2026 Controller of Budget Review)
Other · 2026
A national review by Controller of Budget Margaret Nyakang'o placed Kitui among counties with the largest stalled-project totals nationally (KES…
View trackerWhat has happened since devolution: county and national government projects tracked by status, from launch through completion (or not).
Other · 2026
A national review by Controller of Budget Margaret Nyakang'o placed Kitui among counties with the largest stalled-project totals nationally (KES…
View trackerHealth Facility · 2024
The Auditor-General flagged stalled health projects and contractor site-abandonment worth KES 404.5 million. Physical verification in September 2024 found a…
View trackerRoad Project · 2022
Rebuilding this bridge has dragged on for years since a school bus plunged into the flooded Enziu River in December…
View trackerWater Project · Mbitini · 2026
Commissioned as part of Governor Julius Malombe's water, health and youth empowerment initiatives. Set to serve an estimated 350 households.
View trackerCourt Case · 2020
In a 17 March 2026 ruling, the High Court set aside an earlier ex-parte judgment against the County Government of…
View trackerRoad Project · Mui · 2026
County Government of Kitui (Office of the Governor) put this drift-and-culvert road structure out to open tender in April 2026,…
View trackerWater Project · Athi · 2014
Commissioned by Governor Julius Malombe, in partnership with World Vision Kenya, providing clean water to over 100,000 residents. First launched…
View trackerWater Project · Voo/Kyamatu · 2026
Commissioned by Governor Julius Malombe. Serves approximately 1,100 residents and more than 2,350 livestock.
View trackerWater Project · Kisasi · 2026
Equipped by the County Government of Kitui through the Ministry of Water, commissioned by Kisasi Ward MCA Nicholas Mutemi.
View trackerHealth Facility · 2024
The Auditor-General flagged stalled health projects and contractor site-abandonment worth KES 404.5 million. Physical verification in September 2024 found a…
View trackerOther · 2026
A national review by Controller of Budget Margaret Nyakang'o placed Kitui among counties with the largest stalled-project totals nationally (KES…
View trackerRoad Project · Zombe · 2025
Kitui East MP Nimrod Mbai welcomed continuing progress on the tarmacking works as of late May 2026, describing it as…
View trackerRoad Project · 2023
A national government flagship road project reported "steadily progressing" and nearing completion as of late May 2026, expected to boost…
View trackerRoad Project · Mutha · 2025
Kenya National Highways Authority (Kenha) invited bids to tarmac this road ahead of a planned presidential launch - one of…
View trackerBursary Round · 2025
Kitui Central MP Benson Makali Mulu publicly flagged that bursary fund disbursement timing lagged the academic calendar, saying at least…
View trackerOther · 2015
Kitui Central Constituency was awarded a certificate as the Best Evaluated Constituency in the Eastern region for FY 2014/2015 in…
View trackerWater Project · Kitui Township · 2025
Commissioned by Petroleum Principal Secretary Mohamed Liban, implemented by the Kenya Pipeline Foundation - the 10th borehole under its community…
View trackerRoad Project · 2022
Rebuilding this bridge has dragged on for years since a school bus plunged into the flooded Enziu River in December…
View trackerWater Project · Kisasi · 2007
NG-CDF-funded piping project to provide domestic water, recorded as complete.
View trackerWater Project · Kisasi · 2008
NG-CDF-funded piping project to provide domestic water; recorded as ongoing in Mzalendo's project database.
View trackerWater Project · Mulango · 2005
NG-CDF-funded piping project to provide domestic water, recorded as complete - one of the earliest NG-CDF projects on record for…
View trackerNG-CDF Project · Kisasi · 2005
Classroom construction to improve education facilities; recorded as ongoing against a larger estimated total cost.
View trackerNG-CDF Project · Kibwea · 2008
NG-CDF-funded classroom construction, recorded as complete.
View trackerNG-CDF Project · Kyangwithya West · 2016
Constructed by Kitui Central NG-CDF and handed over to the school community on 18 January 2016.
View trackerNG-CDF Project · Mulango · 2019
A block of five classrooms constructed by NG-CDF, handed over to the community on 7 October 2019.
View trackerNG-CDF Project · Mulango · 2021
Science laboratory constructed by NG-CDF, handed over to the school community on 10 September 2021.
View trackerWater Project · Mulango · 2016
Water project funded by NG-CDF and handed over to the community on 25 February 2016.
View trackerNG-CDF Project · Kitui Township · 2020
Lecture hall at the Kenya Medical Training College (KMTC) Kitui campus, constructed by NG-CDF and handed over on 17 January…
View trackerNational Government Constituency Development Fund allocations, by constituency and financial year - the closest thing to a citable "constituency performance" figure that exists in public records.
| Financial year | Amount |
|---|---|
| FY 2024/25 | KES 179,441,955 |
Source: EducationNews.co.ke (NG-CDF Board FY2024/2025 allocation breakdown)
| Financial year | Amount |
|---|---|
| Cumulative, FY 2013/14 - FY 2024/25 | KES 12,200,000,000 |
Source: BusinessRadar.co.ke, "Counties That Have Gotten the Most NG-CDF Cash Since 2013"
| Financial year | Amount |
|---|---|
| FY 2024/25 | KES 188,414,052 |
Source: EducationNews.co.ke (NG-CDF Board FY2024/2025 allocation breakdown)
| Financial year | Amount |
|---|---|
| FY 2022/23 | KES 138,215,033 |
| FY 2023/24 | KES 166,593,720 |
| FY 2024/25 | KES 170,469,857 |
| FY 2025/26 | KES 182,982,585 |
Source: Mzalendo.com (NG-CDF Board data, independently checked) EducationNews.co.ke (NG-CDF Board FY2024/2025 allocation breakdown)
| Financial year | Amount |
|---|---|
| FY 2024/25 | KES 188,414,052 |
Source: EducationNews.co.ke (NG-CDF Board FY2024/2025 allocation breakdown)
| Financial year | Amount |
|---|---|
| FY 2024/25 | KES 170,469,857 |
Source: EducationNews.co.ke (NG-CDF Board FY2024/2025 allocation breakdown)
| Financial year | Amount |
|---|---|
| FY 2022/23 | KES 151,960,174 |
| FY 2023/24 | KES 184,129,901 |
| FY 2025/26 | KES 202,243,910 |
Source: Mzalendo.com (NG-CDF Board data, independently checked)
| Financial year | Amount |
|---|---|
| FY 2024/25 | KES 179,441,955 |
Source: EducationNews.co.ke (NG-CDF Board FY2024/2025 allocation breakdown)
| Financial year | Amount |
|---|---|
| FY 2024/25 | KES 170,469,857 |
Source: EducationNews.co.ke (NG-CDF Board FY2024/2025 allocation breakdown)
No published per-ward funding series exists anywhere for comparison - this instead counts real projects this site has actually tracked, per ward. A ward with zero here may simply not have a tracked project yet, not zero activity.
| Ward | Tracked projects | Statuses |
|---|---|---|
| Kisasi | 4 | Ongoing, Completed |
| Mulango | 4 | Completed |
| Kitui Township | 2 | Completed |
| Mui | 1 | Ongoing |
| Mutha | 1 | Ongoing |
| Zombe | 1 | Ongoing |
| Mbitini | 1 | Completed |
| Kyangwithya West | 1 | Completed |
| Kibwea | 1 | Completed |
| Voo/Kyamatu | 1 | Completed |
| Athi | 1 | Completed |